Core Refusal Reason
Failure to demonstrate that the existing wastewater treatment infrastructure is adequate to accommodate the development without posing a risk to public health or the environment.
Decision Maker's Conclusion
- The applicant failed to comply with a prior planning condition (Reg Ref: F04A/0683) requiring an independent engineer's report on the operation and environmental impact of the existing treatment plant.
- Insufficient information was provided to prove that the hotel's wastewater infrastructure can facilitate additional development, rendering the proposal prejudicial to public health.
- The development fails to meet the requirements of Objective DMSO196 of the Fingal Development Plan 2023-2029 regarding the safe disposal of wastewater on-site.
Cited Policies (CDP)
Objective DMSO196
Decision Document Summary
The application sought retention permission for works conducted in the northern rear outdoor area of The Shoreline Hotel, Donabate. The proposal was refused by the Planning Authority because the applicant failed to demonstrate that the existing on-site wastewater treatment system is capable of handling the additional load. Due to the lack of technical evidence regarding the plant's adequacy and the potential risk to the surrounding environment and public health, the development was deemed contra...SOURCE PDFOpen Original