227012

extension of duration for 11/1066 for construction of a digester plant, associated ABP building and associated site works to process farm slurry and other organic material to provide renewable energy and fertilizer

Refused

Core Refusal Reason

The application failed to meet the statutory requirements for an extension of duration as the development has not commenced and no substantial works have been carried out on-site.

Decision Maker's Conclusion

  • The applicant explicitly confirmed on the application form that no works have commenced on the permitted development to date.
  • The proposal does not satisfy the mandatory requirements of Section 42B(1B)(v)(I) and (II) of the Planning and Development Act 2000 (as amended).
  • Under current legislation, an extension of duration cannot be granted unless the planning authority is satisfied that the development has commenced and substantial works were carried out prior to the expiration of the permission.

Cited Policies (CDP)

Decision Document Summary

This application sought a further extension of duration for a digester plant, associated ABP building, and site works at Killuragh, Pallasgreen, Co. Limerick, originally permitted under Ref: 11/1066 and previously extended under Ref: 17/7026. The Limerick City & County Council refused the application because the development has not yet commenced. As no substantial works have been performed, the proposal fails to meet the legal criteria set out in Section 42 of the Planning and Development Act 20...
SOURCE PDFOpen Original