22859

to construct 4 No. detached dwellings, entrance road, paths, public lighting & all associated site works and services. Gross floor space of proposed works: 541.2sqm

Refused

Core Refusal Reason

The development is considered premature due to unresolved technical issues regarding the feasibility of the wastewater network and the failure to secure necessary wayleaves for servicing.

Decision Maker's Conclusion

  • The proposal is premature pending satisfactory details regarding the feasibility of the existing wastewater network, particularly concerning potential negative gradients within the system.
  • The applicant failed to address the requirement for consents and wayleaves over third-party lands necessary to secure the wastewater servicing for the proposed development.
  • Granting permission would be prejudicial to public health and would conflict with the proper planning and sustainable development of the area as set out in the County Development Plan.

Cited Policies (CDP)

Policy Objective RC 2Policy Objective NBH 1Policy Objective NHB 3Policy Objective WR 1Policy Objective LCM 3Policy Objective WW 6Policy Objective WW 11DM Standard 7DM Standard 8DM Standard 9DM Standard 11DM Standard 28DM Standard 29DM Standard 36DM Standard 38DM Standard 46DM Standard 47DM Standard 50DM Standard 61DM Standard 63DM Standard 67

Decision Document Summary

The applicant sought permission for the construction of 4 detached dwellings and associated site works on a 0.33ha site located off the R351 Regional Road within the settlement boundary of Woodford, Co. Galway. Although the development was considered acceptable in principle and design, the Planning Authority refused permission following a further information request. The refusal was based on the lack of evidence regarding the feasibility of the wastewater connection, specifically concerns raised...