FIVE YEAR PERMISSION FOR DEVELOPMENT OF A TEMPORARY TURNING HEAD AT THE R312 AND R317 JUNCTION, REQUIRED TO FACILITATE THE DELIVERY OF TURBINE COMPONENTS TO THE CONSENTED SHESKIN WIND FARM (P19/457). LOCALLY SOURCED GRAVEL WILL BE USED TO WIDEN THE JUNCTION SO DELIVERY VEHICLES CAN PERFORM A TURNING MANOEUVRE. THE LAND REQUIRED FOR THE TURNING HEAD WILL BE REINSTATED SHORTLY AFTER THE TURBINE COMPONENTS HAVE BEEN DELIVERED
Granted
Analysis not available for this case.
Decision Document Summary
No text availableSOURCE PDFOpen Original