211669
a temporary period of up to 5 years for the development of 3no. hydrokinetic turbines, associated anchors and marker buoys upstream of Thomond Weir in the River Shannon, a junction box and cable carrying metal conduit along a section of Thomond Weir, connection of the cable to the ESB building on Brown's Quay, placement of power conditioning and power storage unit within the building and the placement of a portacabin in the grounds of the ESB building at Brown's Quay, Limerick City. The project will be for 24 months. A Foreshore Licence Application has been submitted for this development. An Environmental Impact Screening Report, an Ecological Impact Assessment Report and a Natura Impact Statement accompanies this application
Granted
Analysis not available for this case.
Decision Document Summary
No text availableSOURCE PDFOpen Original
Note: If code appears below, the council site is blocking the preview. Please open the original file.