21479

Development consisting of the construction of 1 No. dwelling house incorporating domestic garage and wastewater treatment system with raised soil polishing filter, including all other ancillary site work and services

Refused

Core Refusal Reason

The applicant failed to demonstrate a genuine rural housing need for a dwelling in a designated green belt area as required by the Sligo County Development Plan.

Decision Maker's Conclusion

  • The applicant does not meet the specific criteria for a one-off rural house in a green belt area under Policy P-GBSA-HOU-1, as they are currently employed in Dublin and the landholding is not associated with their principal family residence.
  • The proposed development would constitute inappropriate housing in a rural area lacking essential public services, leading to an uneconomic demand for the future provision of such infrastructure.
  • Granting permission would militate against the preservation of the rural environment and set an undesirable precedent for further unsustainable development within the Enniscrone buffer zone.

Cited Policies (CDP)

Section 5.3.1P-GBSA-HOU-1Section 13.4Section 5.3.2P-RHOU-2Section 13.4.2Section 3.3.3 (Enniscrone LAP)Policy HP-6 (Enniscrone LAP)

Decision Document Summary

The applicant sought permission for a single-storey dwelling, garage, and wastewater treatment system at Bunnanilra, Enniscrone, Co. Sligo. The site is situated within a designated green belt/buffer zone where residential development is strictly controlled. Sligo County Council refused the application because the applicant failed to demonstrate a functional or social 'rural housing need' in accordance with Policy P-GBSA-HOU-1. The planner noted the applicant works in Dublin and the land was acqu...