EXTENSION OF DURATION OF 17/332 - Permission for development to consist of Solar PV Energy Development of maximum export capacity 4MW to include photovoltaic panels on ground mounted frames/support structures; one ESB Networks substation building with a height not exceeding 4m; underground cabling and ducting; 3 no. inverter/transformer/storage stations with a height of 2.7m; perimeter (stock proof) security fencing; security cameras; site access; temporary construction compound
Refused
Core Refusal Reason
The development had not commenced on-site, and legislative amendments to Section 42 of the Planning and Development Act 2000 removed the provision to extend permissions for un-commenced developments where substantial works have not been carried out.
Decision Maker's Conclusion
- The development granted under planning reference 17/332 has not commenced on-site, and no substantial works have been carried out to date.
- Legislative amendments effective from 9th September 2021 deleted the provision allowing for the extension of duration for un-commenced developments, making the request legally impermissible.
- Considerations of an economic nature, such as being unsuccessful in a renewable energy support scheme auction, cannot be considered as grounds for extension under the updated statutory framework.
Cited Policies (CDP)
Decision Document Summary
This application sought a five-year extension of duration for a previously granted 4MW solar PV energy development at Drumcar Road, Dunleer (Ref: 17/332). The applicant, Peter Dunne, cited failure to secure a renewable energy support scheme auction as the primary reason for the delay in commencement. Louth County Council refused the extension because no physical works had started on-site. Under Section 28(1) of the Planning and Development (Housing) and Residential Tenancies Act 2016 (as amended...SOURCE PDFOpen Original