Core Refusal Reason
The application for an extension of duration was refused because the development had not commenced and no substantial works were carried out prior to the expiration of the original planning permission, as required under Section 42 of the Planning and Development Act 2000 (as amended).
Decision Maker's Conclusion
- The development to which permission P16/555 relates was not commenced before the expiration of the appropriate period.
- No substantial works were carried out pursuant to the original planning permission during its valid term.
- The application fails to meet the mandatory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000 (as amended) for an extension of duration.
Cited Policies (CDP)
Decision Document Summary
Crowes Ministers Cross Ltd sought an extension of duration for planning permission P16/555, which authorized the construction of a tyre repair and replacement garage facility at Cloghlea, Sixmilebridge, Co. Clare. The Planning Authority refused the request because the applicant failed to demonstrate that the development had commenced or that substantial works had been undertaken before the original permission expired on March 9th, 2022. Furthermore, recent legislative changes removed the provisi...SOURCE PDFOpen Original