22421

EXTENSION OF DURATION OF 17/332 - Permission for development to consist of Solar PV Energy Development of maximum export capacity 4MW to include photovoltaic panels on ground mounted frames/support structures; one ESB Networks substation builiding with a height not exceeding 4m; underground cabling and ducting; 3 no. inverter/transformer/storage stations with a height of 2.7m; perimeter (stock proof) security fencing; security cameras; site access; temporary construction compound

Refused

Core Refusal Reason

The applicant failed to demonstrate that substantial works were carried out pursuant to the permission during the appropriate period, as required by Section 42(1)(a)(i) of the Planning and Development Act 2000 (as amended).

Decision Maker's Conclusion

  • The Planning Authority is not satisfied that substantial works have been carried out pursuant to the permission during the appropriate period as required by statute.
  • Insufficient documentary evidence was provided to confirm the project's successful status and final results within the EirGrid Renewable Electricity Support Scheme (RESS 2) Qualification Process.
  • While the application complies with environmental requirements regarding EIA and AA, it fails to meet the mandatory threshold for works completed to justify an extension of duration.

Cited Policies (CDP)

Decision Document Summary

This application sought an extension of duration for a previously granted 4MW solar PV energy development at Drumcar Road, Dunleer, Co. Louth (Original Ref: 17/332). The project includes ground-mounted solar panels, an ESB substation, and associated infrastructure. Although the development was noted to have commenced in November 2021, the planning authority determined that the works performed did not meet the 'substantial' threshold required under Section 42 of the Planning and Development Act. ...