Extension of Duration of Planning File 17/276

Refused

Core Refusal Reason

The application for an extension of duration was refused because the development had not commenced and substantial works had not been carried out prior to the expiration of the original planning permission, failing to meet the statutory requirements of Section 42 of the Planning and Development Act 2000.

Decision Maker's Conclusion

  • The development to which the permission relates was not commenced before the expiration of the appropriate period, and substantial works were not carried out during that period as required by Section 42(1)(a) of the Act.
  • The applicant failed to provide a projected completion date or specify the duration of the extension sought, preventing the Planning Authority from determining if the development would be completed within a reasonable time.
  • The application failed to comply with Article 42(ff) of the Planning and Development Regulations 2001, as amended, by failing to provide necessary information for a screening determination regarding environmental impact assessment.

Cited Policies (CDP)

Decision Document Summary

This application sought an extension of duration for planning permission (Ref. 17/276) involving the construction of two-storey and single-storey extensions and a garden building at 25 Murphy Place, Abbeyside, Dungarvan. The Planning Authority refused the request following a site inspection which confirmed that only minor site clearance had occurred and no substantial construction works had been carried out before the original permission expired. Additionally, the application was deemed procedur...