22843

to Extend the Appropriate Period of Planning Permission P17/338 to alter and extend an existing dwelling house, install a new waste water treatment system and water facilities along with all associated works

Refused

Core Refusal Reason

The application failed to meet the statutory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000, as no substantial works had been carried out and the development had not commenced prior to the expiration of the original permission.

Decision Maker's Conclusion

  • The development did not commence before the expiration of the original planning permission (P17/338).
  • No substantial works were carried out pursuant to the permission during the appropriate period.
  • The application does not comply with the mandatory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000 (as amended).

Cited Policies (CDP)

Decision Document Summary

This application sought to extend the appropriate period of planning permission P17/338 for the alteration and extension of an existing dwelling house and installation of a new wastewater treatment system at Knocknagarhoon, Kilkee, Co. Clare. The local authority refused the extension because a site inspection confirmed that no works had been carried out to date, and the development had not commenced before the expiration of the original permission. Consequently, the proposal failed to satisfy th...