Core Refusal Reason
The application failed to meet the statutory requirements for an extension of duration under Section 42(1)(a)(i) of the Planning and Development Act 2000, as development had not commenced and no substantial works were carried out prior to the expiration of the original permission.
Decision Maker's Conclusion
- A site inspection conducted on 28.10.2022 confirmed that the applicant has not commenced development on the site.
- The applicant failed to carry out substantial works in the context of the overall development, failing to satisfy Section 42(1)(a)(i)(II) of the Planning and Development Act 2000.
- The proposal does not satisfy the mandatory requirements of Section 42(1) of the Planning and Development Act 2000 (as amended) for the extension of the appropriate period of planning permission.
Cited Policies (CDP)
Decision Document Summary
This application sought an extension of duration for a previously granted permission (Ref. 17600706) for the construction of a dwelling, domestic garage, and septic tank at Fennor, Urlingford, Co. Tipperary. Upon evaluation and site inspection, the Planning Authority determined that no development had commenced and no substantial works had been performed on-site. As the application failed to meet the necessary legal criteria under Section 42 of the Planning and Development Act 2000, the extensio...SOURCE PDFOpen Original