of Planning Permission Reference 18/56

Refused

Core Refusal Reason

The development had not commenced and substantial works had not been carried out prior to the application for an extension of duration, as required under Section 42 of the Planning and Development Act 2000 (as amended).

Decision Maker's Conclusion

  • The development permitted under planning reference P18/56 has not commenced on-site as of the date of the extension application.
  • No substantial works were carried out before the expiration of the appropriate period, failing to meet the statutory requirements for an extension.
  • The Planning Authority is legally precluded from granting an extension of duration under the provisions of Section 42 of the Planning and Development Act 2000-2021.

Cited Policies (CDP)

Decision Document Summary

The applicant, Carmel Brennan, sought a five-year extension of duration for planning permission P18/56, which authorized the construction of a two-storey dwelling, domestic garage, and associated site works at Kilkieran, Ballyfoyle, Co. Kilkenny. The Planning Authority refused the application because the development had not yet commenced and no substantial works had been completed. Under Section 42 of the Planning and Development Act 2000 (as amended), the commencement of development and the com...