to Extend the Appropriate Period of Planning Permission for P17/416 ABP Ref PL03.249071 for (1) the provision of a detached bungalow (140 sqm) including separate connections to the public watermains & public sewer and all associated site works. (2) Relocation of the existing vehicular entrance to no.6 and the provision of an additional vehicular entrance to the proposed dwelling, all to the front of No.6 off Woodlawn on a site to the rear
Refused
Core Refusal Reason
The development had not commenced and no substantial works were carried out prior to the expiration of the original planning permission's appropriate period.
Decision Maker's Conclusion
- The development permitted under P17/416 (ABP Ref PL03.24907) had not commenced prior to the expiration of the appropriate period on 19/03/2023.
- No substantial works were carried out pursuant to the permission during the appropriate period, failing to meet the mandatory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000 (as amended).
- The Planning Authority was not satisfied that the development would be completed within a reasonable time, as the applicant failed to provide a definitive date for the commencement of construction.
Cited Policies (CDP)
Decision Document Summary
Fintan and Kate Molony sought an extension of duration for planning permission P17/416 (ABP Ref PL03.24907) to construct a 140 sqm detached bungalow and associated site works at 6 Woodlawn Loughvilla, Ennis, Co. Clare. The application was refused because a site inspection confirmed that no works had commenced and no substantial works were undertaken before the original permission expired on March 19, 2023. Consequently, the proposal failed to meet the statutory requirements set out in Section 42...SOURCE PDFOpen Original