23236

to Extend the Appropriate Period of Planning Permission for P17-808 for development which will consist of the construction of a new part two-storey, part single-storey house, with a sewage treatment plant and percolation area, new stone boundary walls and a connection driveway, with a new road entrance and associated hard and soft landscaping

Refused

Core Refusal Reason

The application failed to meet the statutory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000, as the development had not commenced and no substantial works were carried out prior to the expiration of the original permission.

Decision Maker's Conclusion

  • The development to which permission Pl. Ref 17/808 relates was not commenced before the expiration of the appropriate period on 28th April 2023.
  • No substantial works were carried out pursuant to the original permission during the appropriate period.
  • Current legislation, following the 2021 amendments to the Planning and Development Act, provides no provision for extending the appropriate period where development has not commenced.

Cited Policies (CDP)

Decision Document Summary

Brian Dowd sought to extend the duration of planning permission (Ref: 17/808) for a two-storey house and associated works at Knocknagroagh, Ballyvaughan, Co. Clare. The application was refused because the development had not commenced and no substantial works were completed before the original permission expired in April 2023. Under current planning legislation, an extension cannot be granted if the development has not yet started....