Core Refusal Reason
The applicant failed to provide sufficient environmental and technical information, specifically regarding Appropriate Assessment and odour management, to demonstrate that the development would not negatively impact Natura 2000 sites or local residential amenity.
Decision Maker's Conclusion
- The lack of an Appropriate Assessment Screening Report prevented a proper evaluation of the development's impact on the River Boyne and River Blackwater SAC/SPA, particularly concerning ammonia emissions and water quality.
- The proposed development failed to adequately address potential odour nuisance, with the submitted screening tool being incomplete and lacking a necessary Odour Management Plan to protect neighbouring residents.
- Insufficient information was provided regarding the identification of spreadlands and the Nutrient Management Plan, which are critical for assessing the environmental sustainability of the pig units.
Cited Policies (CDP)
Decision Document Summary
This application by Michael Murtagh sought the retention of two pig units, meal silos, and associated agricultural infrastructure at Newtown, Mullingar, Co. Westmeath. The 0.77ha site is situated in a rural area in close proximity to residential dwellings and the River Boyne and River Blackwater Natura 2000 sites. Although the principle of agricultural development was considered acceptable, the application was refused due to significant gaps in environmental documentation. Specifically, the appl...SOURCE PDFOpen Original