2360124
the proposed development will comprise: • the replacement (“restringing”) of the existing overhead line circuit conductor wires with a new higher capacity conductor including installation of a new fibre communication connection; • the replacement of 52no. existing polesets and 4no. towers - any replacement structures will be constructed at, or immediately adjacent to the existing structures they will replace, will be along the same alignment as existing; • the replacement of angle mast AM3A with a poleset; • the retention and refurbishment, steel member replacement, painting and foundation strengthening of the one retained end mast EM1; • the replacement of hardware and fittings at all structure locations; • the replacement of stay arrangements at 27no. locations; • the replacement of crossarms at 27no. locations; • the installation of insulators at 13no. locations; • the replacement of vibration dampers at 12no. locations; • the reinstallation of all anti-climbing guards; • the reinstallation of aircraft warning spheres at span 127-128; • all associated works within the existing Lanesboro 110 kV substation to accommodate the uprated 110 kV OHL including uprating of the Mullingar bay in Lanesboro 110 kV substation, routing of fibre optic cable from end mast into substation and alterations to existing hardware; • all associated temporary site development works to gain access to the existing structures including clearance of vegetation, disassembly and reassembly of gate posts / piers and removal and reinstatement of existing fencing; and • other temporary associated and ancillary site development works required for the purpose of the uprate of the existing circuit, including construction compounds, silt traps, silt fences, stone tracks, ground protection mats, infrastructure crossing support systems and temporary watercourse crossings