Core Refusal Reason
The application failed to meet the statutory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000 (as amended) as no substantial works had been carried out and the development would not be commenced before the expiration of the original permission.
Decision Maker's Conclusion
- The development to which permission P18/591 relates was not commenced before the expiration of the appropriate period sought to be extended.
- No substantial works were carried out pursuant to the original permission during the appropriate period.
- The application does not comply with the mandatory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000, as amended, which governs the extension of the appropriate period of a planning permission.
Cited Policies (CDP)
Decision Document Summary
This application sought a 12-month extension of the appropriate period for planning permission P18/591, which authorized the construction of a single dwelling house, garage, and wastewater treatment system at Ballykildea, Killaloe, Co. Clare. Following a site inspection, the Planning Authority determined that no works had been carried out to date. Consequently, the proposal was refused as it failed to satisfy the statutory criteria under Section 42(1)(a)(i) of the Planning and Development Act 20...SOURCE PDFOpen Original