24118
(A) THE REMOVAL OF A MAST SUPPORTED TENSILE CANVAS FRONT ENTRANCE CANOPY, (B) TO CONSTRUCT A SINGLE STOREY EXTENSION THE FRONT OF THE DINGLE OCEANWORLD COMPLEX TO ALLOW FOR A NEW PUBLIC ENTRANCE FOYER, (C) NEW SINAGE ERECTED ON THE ABOVE NEW STRUCTURE, AND (D) ALLOW FOR THE REDESIGN OF THE WING WALLS AT THE PEDESTRIAN PUBLIC ENTRANCE TO ALLOW FOR A NEW STEPPED ACCESS ROUTE FROM THE PUBLIC FOOTPATH AND ALL ASSOCIATED EXTERNAL WORKS
Granted
Core Planning Reasoning
The provided Planner's Report recommends a grant of permission; therefore, no refusal reasons are contained within the document.
Decision Maker's Conclusion
- The proposed development is located on land zoned M4 Built Up Area, where the proposal is considered acceptable in principle and consistent with the Corca Dhuibhne FALAP 2021-2027.
- The visual impact of the single-storey extension and removal of the canopy is rated as acceptable and is expected to have a positive impact on the structure and surrounding area.
- The development is not expected to negatively impact residential amenities, road safety, or Natura 2000 sites, and connects to existing public sewer and water mains.
Cited Policies (CDP)
Kerry County Development Plan 2015-2021Corca Dhuibhne Electoral Area Local Area Plan 2021-2027M4 Built Up Area zoningKCC Shopfront Design Guidelines
Decision Document Summary
The planning application (File No. 24/118) by Mara Beo Teo seeks permission for the removal of a tensile canvas canopy and the construction of a 104sqm single-storey entrance foyer extension at the Dingle Oceanworld complex in The Wood, Dingle. The proposal also includes new signage and the redesign of wing walls for a new stepped access route. Although the user indicates the application was refused, the attached Planner's Report recommends a grant of permission, concluding that the project is c...SOURCE PDFOpen Original