Core Refusal Reason
Failure to submit requested further information within the statutory four-week timeframe regarding the progress and completion timeline of the development.
Decision Maker's Conclusion
- The applicant failed to provide a schedule of works carried out to date pursuant to the original permission (Ref. D16A/0783).
- No written confirmation was provided regarding the owner's intention or ability to complete the permitted development within a reasonable timeframe.
- The application was refused under Article 45(3) of the Planning and Development Regulations because the requested further information was not submitted within the mandatory 4-week deadline.
Cited Policies (CDP)
Decision Document Summary
This application sought a further extension of duration for the conversion of Mountainview House, a protected structure in Churchtown, from office to residential use. The Planning Authority issued a request for further information to verify the extent of works completed and to ensure the development would be finished within a reasonable period. Because the applicant failed to respond to this request within the statutory four-week period required by Article 45(3) of the Planning and Development R...SOURCE PDFOpen Original