2460126

development will consist of a mixed use residential/commercial development including 2 No.detached four-bedroom dormer dwellings, 7 No.detached two bedroom single storey dwellings, 10 No.semi-detached three bedroom two storey dwellings, 4 No. terraced two bedroom two storey dwellings, block with 2 No. two bedroom apartments at first floor level and 2 No. 101 sq.m. commercial unit’s at ground floor level, a new vehicular entrance and access road, car parking and bicycle parking, landscaped open space with pedestrian link to adjoining Clog Na Léinn, connections to existing foul sewer via temporary treatment system on adjoining land, surface water drainage systems and all ancillary services

Refused

Core Refusal Reason

The proposed development is considered premature due to the lack of capacity in the existing Collinstown wastewater treatment plant and the high groundwater vulnerability of the site.

Decision Maker's Conclusion

  • The existing Collinstown wastewater treatment plant is currently overloaded and upgrades are not anticipated until after 2030, making the development premature.
  • The proposed use of a temporary on-site treatment system is unacceptable given the site's classification as having 'High' groundwater vulnerability.
  • The development is contrary to Westmeath County Development Plan 2021-2027 policies CPO 10.94 and CPO 10.99, which require sufficient public infrastructure capacity and protect against increased effluent loading in vulnerable areas.

Cited Policies (CDP)

CPO 10.94CPO 10.99CPO 2.11CPO 2.14CPO 2.20CPO 3.2CPO 10.96CPO 15.6Section 8.6.5

Decision Document Summary

N.J. Doyne Construction (Ireland) Ltd sought permission for a mixed-use development comprising 25 residential units and two commercial units on an infill site at Mullingar Road, Collinstown, Co. Westmeath. While the layout was acknowledged as a natural extension of the village, the application was refused primarily due to inadequate wastewater infrastructure. The local treatment plant is at capacity with no upgrades planned until 2030, and the proposed temporary mitigation was deemed unsuitable ...