F22A/0443

Construction of new detached two storey dwelling house, to side of exi

Refused

Core Refusal Reason

The applicant failed to demonstrate a rural housing need and has previously been granted permission for a dwelling in the rural area, violating the policy that limits individuals to a single planning permission for a house in such zones.

Decision Maker's Conclusion

  • The applicant failed to submit the mandatory 'Supplementary Application Form' and supporting documentation required to demonstrate compliance with the Rural Settlement Strategy for the South Shore area of Rush.
  • The proposed site access, transportation arrangements, and landscaping plans were deemed inadequate, lacking necessary technical details such as swept path analysis and professional design specifications.
  • The proposal represents a material contravention of the Fingal Development Plan 2023-2029 because the applicant's housing need was already satisfied by a previous grant of permission (F05A/0646), exceeding the one-house-per-applicant limit.

Cited Policies (CDP)

Objective RF43Section 3.5.15.3Fingal Development Plan 2023-2029

Decision Document Summary

The proposal involved the construction of a new detached two-storey dwelling house to the side of an existing property at Padre Pio, Channel Road, Rush, Co. Dublin. The site is situated within a rural zoned area of the South Shore, where residential development is strictly controlled by the Fingal Rural Settlement Strategy. The Planning Authority refused permission because the applicant had already received a prior grant for a permanent residence in the area, thus failing to meet the 'one house'...
SOURCE PDFOpen Original
Note: If code appears below, the council site is blocking the preview. Please open the original file.