24226

to Extend the Appropriate Period of Planning Permission P18/580 for the construction of 3 no. detached dwellings and all associated site development works

Refused

Core Refusal Reason

The application failed to meet the statutory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000 (as amended) because no substantial works had been carried out and the development would not commence before the expiration of the original permission.

Decision Maker's Conclusion

  • The Planning Authority is not satisfied that the development to which permission P18/580 relates was commenced or will commence before the expiration of the appropriate period.
  • No substantial works were carried out pursuant to the original permission during the appropriate period as confirmed by a site inspection.
  • The application does not comply with the mandatory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000, as amended, which is necessary to permit an extension of duration.

Cited Policies (CDP)

Decision Document Summary

ODM Properties Ltd. sought a three-year extension of the appropriate period for planning permission P18/580, which authorized the construction of three detached dwellings at Ard na Deirge, Killaloe, Co. Clare. Following a site inspection, the Planning Authority determined that no works had been carried out on-site to date. Consequently, the application was refused as it failed to satisfy the statutory requirements of Section 42(1)(a)(i) of the Planning and Development Act 2000 (as amended), whic...