Core Refusal Reason
The proposed development is located within the corridor of the proposed Limerick Northern Distributor Road (LNDR) and is considered premature pending the finalization of the road layout.
Decision Maker's Conclusion
- The application site is situated within the identified corridor for the Limerick Northern Distributor Road (LNDR) strategic infrastructure project.
- The proposed development is considered premature until the Planning Authority has determined the final road layout and design for the area.
- Granting permission would prejudice the delivery of this strategic transport route and would therefore be contrary to the proper planning and sustainable development of the area.
Cited Policies (CDP)
Decision Document Summary
Siarhei Novik sought permission for the construction of a storage shed with a workshop, a new septic tank, and a new entrance at Ballyguy, Murroe, Co. Limerick. The site is located in a rural area within the Limerick City East planner area. The application was refused by the local authority primarily because the site falls within the corridor of the proposed Limerick Northern Distributor Road (LNDR), making the development premature and potentially obstructive to strategic infrastructure deliver...SOURCE PDFOpen Original