Core Refusal Reason
The application for an extension of duration was refused because the development had not commenced and no substantial works had been carried out pursuant to the permission, failing to meet the mandatory requirements of Section 42(1) of the Planning and Development Act 2000.
Decision Maker's Conclusion
- The development to which the permission relates, specifically the upgrading of the wastewater treatment system, had not commenced prior to the application for extension.
- No substantial works were carried out pursuant to the permission (PRR 19/42) during the appropriate period.
- The application fails to satisfy the statutory requirements of Section 42(1)(a)(i) and (iii) of the Planning and Development Act 2000 (as amended).
Cited Policies (CDP)
Decision Document Summary
The applicant sought a five-year extension of duration for planning permission (PRR 19/42) to replace an existing septic tank with a new treatment system and sand filter, and to retain existing dwellings at Clearwater, Castletimon, Brittas Bay, Co. Wicklow. The Planning Authority refused the application on the grounds that the development had not commenced and no substantial works had been undertaken on the permitted wastewater treatment system upgrade. As the proposal failed to meet the legisla...SOURCE PDFOpen Original