the development will consist of the construction of a storey and a half style dwelling with single storey projection to the side, a new domestic entrance to the site from an existing laneway, construction of a new detached domestic garage, new wastewater treatment system and all associated site works

Refused

Core Refusal Reason

The proposed development would result in the intensification of an existing entrance onto the N51 national secondary route, a strategic corridor with a speed limit exceeding 60kph, thereby compromising the safety and capacity of the national road network.

Decision Maker's Conclusion

  • The development would lead to an intensification of an existing junction on the N51 national secondary route, which is designated as a Strategic Corridor in the County Development Plan.
  • The proposal is contrary to national guidelines and local policies (RD POL 37 and MOV POL 24) that seek to avoid additional access points or increased traffic on national roads with speed limits over 60kph.
  • The additional turning movements generated by the dwelling would introduce unacceptable safety risks to road users and adversely affect the functionality of the national road network.

Cited Policies (CDP)

RD POL 1RD POL 2RD POL 3RD POL 36RD POL 37MOV POL 24Section 9.4Section 9.5Section 9.15.1Section 9.18

Decision Document Summary

Emma Farrelly sought permission for a storey-and-a-half dwelling, garage, and wastewater system at Ongenstown, Boyerstown, Navan, Co. Meath. The site is located in a rural area under strong urban influence and is accessed via an existing laneway onto the N51 national secondary route. While the Planning Officer was satisfied that the applicant demonstrated a local housing need, the application was refused because the development would result in the intensification of a junction on a strategic roa...