Core Refusal Reason
The proposed development constitutes overdevelopment due to the failure to provide a necessary childcare facility on a site previously designated for such use, leaving the wider residential development of circa 286 dwellings without adequate services.
Decision Maker's Conclusion
- The loss of the site previously designated for a creche facility under parent permission Reg. Ref. 07/1474 results in a deficit of essential community infrastructure for the wider 286-dwelling estate, contrary to Section 28 Guidelines and the Kildare County Development Plan.
- The location of the existing electrical substation to the front of the proposed dwellings is considered to have a significant negative visual impact on the residential amenity of units E1 and F.
- The application failed to provide adequate technical information regarding site-specific soil infiltration for sustainable drainage, a comprehensive construction management plan, and specific details required to establish Part V social housing obligations.
Cited Policies (CDP)
Objective SC O77Objective SC O79Objective HO O23Objective TM O118Section 15.4.6Table 15.8SPPR 2Chapter 3Chapter 10Chapter 15Kill Small Town Plan 2023-2029
Decision Document Summary
Cavan Developments Kill Ltd proposed the construction of 7 terraced houses on a 0.2ha infill site at Kilheale Manor, Kill, Co. Kildare. The site is currently used as a construction compound and was originally identified for a childcare facility in previous planning permissions. The planning authority determined that the proposal constitutes overdevelopment because the wider residential area has not benefited from the inclusion of a childcare facility despite the construction of approximately 286...SOURCE PDFOpen Original