for construction of 10 no. new semi-detached dwellings (5 no. pair 3 bed dormer houses , connection to public services and all ancillary site works to continue and complete existing residential development.

Refused

Core Refusal Reason

The proposed development was deemed premature and contrary to proper planning because it is located within an unfinished housing estate with substandard infrastructure, and it failed to meet visual, traffic, and Gaeltacht linguistic policy requirements.

Decision Maker's Conclusion

  • The development is premature as the existing housing estate remains unfinished, with roads and services that are not of a 'taking in charge' standard, negatively impacting residential amenity.
  • The proposal would result in a significant adverse visual impact on a prominent, sensitive site located along a designated 'Scenic Route'.
  • The applicant failed to demonstrate compliance with Gaeltacht linguistic protection objectives and did not provide evidence of technical feasibility for water and sewerage connections from Uisce Éireann.

Cited Policies (CDP)

Policy H 34Objective GDD01DMURSWaterford City and County Development Plan 2022-2028

Decision Document Summary

Cill Rio Ltd sought permission for 10 semi-detached dormer dwellings to complete an existing residential development at Cluain na si, Shancloon, Ring, Co. Waterford. The site is located in a sensitive Gaeltacht area on an elevated position along a designated scenic route. Waterford City and County Council refused the application primarily because the existing estate remains unfinished with substandard infrastructure that has not been brought to a 'taking in charge' standard. Additionally, the pr...