2460287

- Replacement (“restringing”) and uprating of the conductor on the existing Athlone-Lanesboro 110 kV overhead line circuit, measuring approximately 0.12km in length; - Provision of fibre communication connection on the uprated circuit; -Completion of foundation strengthening and bar member replacements to 1No. end mast within the existing Lanesboro 110 kV substation; and -All associated development, including providing an access track and temporary construction compounds, to facilitate the proposed development. A Natura Impact Statement (NIS) has been prepared to accompany this planning application

Granted
Analysis not available for this case.

Decision Document Summary

No text available