2520

upgrade works to improve water quality, comprising upgrade of raw water pumps, installation of equipment to improve process including a new flocculation tank, clarification tank, rapid gravity filters, UV reactor and associated pumps, and accessories. Construction of solids management consisting of tank for settlement and associated pumps and infrastructure. Reservoir tank improvement including pump pipework mixer, and all associated ancillary works and associated engineering works including upgrade to pump house machinery. All works will be conducted within the existing GWS site and pumphouse

Granted
Analysis not available for this case.

Decision Document Summary

No text available
SOURCE PDFOpen Original
Note: If code appears below, the council site is blocking the preview. Please open the original file.