a Section 254 Licence for 1.The erection of new overground fibre optic cables on existing timber poles. 2.The erection of new poles and associated fibre optic cables MRL 2025WD0115

Refused

Core Refusal Reason

Failure to demonstrate sufficient legal interest to carry out the proposed development on public lands.

Decision Maker's Conclusion

  • The applicant failed to provide the necessary consent from Waterford City and County Council to carry out the development on public lands.
  • The developer did not demonstrate sufficient legal interest to execute the proposed development in its entirety.
  • Due to the lack of demonstrated legal interest, the proposal is considered contrary to the proper planning and sustainable development of the area.

Cited Policies (CDP)

Policy UTL 16

Decision Document Summary

National Broadband Ireland applied for a Section 254 Licence to install approximately 72.8km of overground fibre optic cabling and 12 new poles in a rural area of the Comeragh District, east of Kill village. Although the project aligns with the strategic aims of Policy UTL 16 regarding telecommunications infrastructure, the application was refused. The primary grounds for refusal were the applicant's failure to demonstrate sufficient legal interest or obtain specific consent from the local autho...