2560155

a 10 year permission for a Battery Energy Storage system. The proposed development will comprise of the following; A Battery Energy Storage System with associated infrastructure including a new internal access road, approximately 50 metres in length to the permitted Garreenleen Solar Farm (Planning Ref. 22163); An approximately 90 metre 33kV double circuit underground cable grid connection to the permitted Bendinstown 110kV Substation (Planning Ref. ABP–313139), to be installed in an excavated trench including underground ducting; Modular office and welfare buildings; Six steel storage containers and all associated site development and reinstatement works. A Natura Impact Statement (NIS) has been prepared and is included with this planning application.

Refused

Core Refusal Reason

The applicant failed to provide a comprehensive Archaeological Impact Assessment (AIA) and test excavations to ensure the protection of nearby Recorded Monuments and potential subsurface archaeological remains.

Decision Maker's Conclusion

  • The development is located in close proximity to Recorded Monuments CW013-023001 (Church) and CW013-023003 (Graveyard), and in the absence of an Archaeological Impact Assessment, the potential for disturbance of subsurface remains cannot be ruled out.
  • The proposal materially contravenes policies AH.P1, AH.P3, and AH.P4 of the Carlow County Development Plan 2022-2028, which mandate the preservation and protection of archaeological heritage and monuments.
  • Granting permission without the required archaeological assessments would set an undesirable precedent for future developments and would be contrary to the proper planning and sustainable development of the area.

Cited Policies (CDP)

AH.P1AH.P3AH.P4EI. P1E1. P2CA. P2RE. P1RE. P2RE. O1IF P1SE. P2SE. O1LA P1LA P2LA P6LA P8

Decision Document Summary

Orsted Onshore Ireland Midco Limited proposed a 10-year permission for a Battery Energy Storage System (BESS) and associated infrastructure on a 3.8ha site in the rural townlands of Gilbertstown and Bendinstown, Co. Carlow. The site is situated adjacent to a permitted solar farm and in close proximity to two recorded archaeological monuments. While the development aligns with renewable energy objectives, it was refused because the applicant did not submit an Archaeological Impact Assessment or c...