2560516
- 2 no. warehouse buildings with a gross floor area (GFA) of c. 3,364 sq.m each and a total height of c. 14.1m. Each warehouse includes a warehouse area of c. 2,419 sq.m, reception area, office, staff facilities, toilets, plant and storage areas at ground floor level, and office space, meeting rooms, staff facilities, toilets, plant and storage facilities at mezzanine level (c. 581 sq.m). - The provision of a service yard with a security hut (c. 34 sq.m) located at the main entrance, HGV unloading areas and 4 no. associated loading bay docks on the eastern elevation of each warehouse building. - The provision of 68 no. car parking spaces including 4 no. accessible spaces and 10 no. EV parking spaces serving staff and visitors. - The provision of 40 no. cycle parking spaces serving staff and visitors. - The provision of a sprinkler tank, sprinkler pump house (c. 13.3 sq.m), fire hydrant tank, hydrant pump house (c. 13.3 sq.m) and ESB substation (c. 25 sq.m) - Construction of a solar farm development consisting of photovoltaic (PV) panel arrays covering an area of approximately c. 15.7 ha on ground mounted steel frames, associated power trunk building (c. 539 sq.m) and 2 no. transformer compounds, underground cabling and ducting, new internal tracks for maintenance and all associated site services works. - Site access from the permitted development to south (WCC Reg. Ref.: 20/1088 as amended WCC Reg. Ref.: 23/62 and 24/88), which is subject to a current separate amendment application under WCC Reg. Ref.: 25/60350, and extension of the permitted inner relief road through the site. - The provision of a new statcom compound including a single storey control and valve building with a GFA of c. 253 sq.m and associated equipment adjacent to the permitted inner relief road to the south of the main site area. The proposed development also includes for the provision of associated landscaping and planting, berms, boundary treatments, internal road network, pedestrian and cyclist infrastructure, signage zones, site lighting, drainage works, sustainable drainage systems (SuDS) and all ancillary site development works
Core Refusal Reason
The proposed development, particularly the large-scale solar farm, contravenes the strategic 'Special Employment' and 'Mixed Use' zoning objectives of the Arklow & Environs Local Area Plan by underutilising land intended for high-intensity employment and potentially impacting the delivery of the residential core strategy.
Decision Maker's Conclusion
- The provision of a solar array on 15.4ha of land zoned for 'Special Employment' and 'Mixed Use' contravenes the specific zoning objectives intended to facilitate large-scale, high-intensity employment and residential growth.
- The proposal fails to achieve a suitable jobs-to-land ratio, representing an underutilisation of strategic employment land that would undermine the economic strategy and future economic activity of the area.
- The development is inconsistent with the vision for Action Area Plan 2 and could negatively impact the delivery of the residential core strategy by encroaching on lands suitable for housing and community services.