2584

extend duration of planning permission Ref. 19/535

Refused

Core Refusal Reason

The application for an extension of duration was refused because the Planning Authority determined that an Appropriate Assessment is required, which legally precludes an extension under Section 42(8) of the Planning and Development Act 2000 (as amended).

Decision Maker's Conclusion

  • The proposed extension of duration relates to a development where the parent application (19/535) originally required a Natura Impact Statement due to its proximity to the River Barrow and River Nore SAC/SPA.
  • A screening for Appropriate Assessment concluded that the likely effects of the proposed development on the Natura 2000 network are uncertain, thereby necessitating a full Appropriate Assessment.
  • Under Section 42(8) of the Planning and Development Act 2000 (as amended), a planning authority is prohibited from extending the appropriate period of a permission if an Appropriate Assessment or Environmental Impact Assessment is required.

Cited Policies (CDP)

Decision Document Summary

This application sought an extension of duration for planning permission (ref: 19/535) to complete the final house (No. 20 Rathvarna) of a 15-house development at The Quakers, Killeshin, Co. Laois. Although the Executive Planner initially recommended a three-year extension, the Senior Executive Planner overturned this recommendation following an Appropriate Assessment screening. The screening found that potential impacts on nearby Natura 2000 sites were uncertain, meaning a full Appropriate Asse...
SOURCE PDFOpen Original
Note: If code appears below, the council site is blocking the preview. Please open the original file.