2660153

of an existing 80m high lattice type meteorological mast and associated instruments, for a period of two years

Refused

Core Refusal Reason

The application for the retention of an 80m meteorological mast was recommended for refusal for a single reason specified in the full planning report.

Decision Maker's Conclusion

  • The development involves the retention of an existing 80m high lattice type meteorological mast and associated instruments for a period of two years.
  • The Executive Planner has formally recommended that permission be refused for the development.
  • The refusal recommendation is based on a single specific reason as documented in the planning authority's full report.

Cited Policies (CDP)

Decision Document Summary

FuturEnergy Ireland Ltd sought planning permission for the retention of an existing 80m high lattice meteorological mast and associated instruments for a two-year period at a site located on a local road. Following an assessment, the Clare County Council planning department recommended refusal of the application. The recommendation, signed by both the Executive and Senior Executive Planners in May 2026, cites a single reason for refusal which is detailed in the accompanying full inspector's repo...