Core Refusal Reason
The development has not commenced and substantial works have not been carried out as required under Section 42 of the Planning and Development Act, 2000 (as amended).
Decision Maker's Conclusion
- The application for an Extension of Duration of planning permission PL21/373 was assessed under the statutory requirements of Section 42 of the Planning and Development Act, 2000 (as amended).
- The Planning Authority determined that the development to which the original permission relates has not yet commenced on the site at Dunroe, Borris.
- As substantial works have not been carried out pursuant to the permission, the mandatory criteria for granting an extension of duration have not been met.
Cited Policies (CDP)
Decision Document Summary
This application sought an Extension of Duration for planning permission PL21/373, which authorized the construction of a single-storey dwelling, effluent treatment system, and vehicular entrance at Dunroe, Borris, Co. Carlow. Carlow County Council refused the request because the development had not commenced and no substantial works had been performed on-site. Consequently, the proposal failed to meet the mandatory legislative criteria set out in Section 42 of the Planning and Development Act, ...SOURCE PDFOpen Original