238002
The development works will consist of: (a) Extension of the existing embankment on the landowner's side. (b) Construction of a shared raised footpath and cycleway, with a macadam-finished surface. The shared path will extend from the roundabout and continue around the bend onto the L-1403 local road. (c) Provision of an uncontrolled crossing on the L-1403 at the end of the proposed footway. (d) Fencing along walkway with timber posts and tensioned mesh fencing on the land-owner's side. (e) Relocation of the existing open drain where required, and piping under access ways into private property. (f) Minor repair works to the N69/L-1403 junction. (g) Accommodation works for affected landowners
Granted
Analysis not available for this case.