Core Refusal Reason
The primary reason for refusal is the lack of adequate road infrastructure serving the site and the applicant's inability to demonstrate control over the lands required to provide a safe and satisfactory means of access.
Decision Maker's Conclusion
- There is a significant deficit in the existing road infrastructure directly serving the subject site.
- The necessary construction and augmentation works required to facilitate appropriate access are located outside the planning unit and are not within the remit or control of the applicant.
- Granting permission would constitute disorderly and haphazard development that would endanger public safety by reason of a traffic hazard or obstruction to other road users.
Cited Policies (CDP)
Section 4.6.2Policy Objective RH 4Section 7.5.3Section 8.13Section 10.6Section 10.15Chapter 12Section 14.4Section 14.6Section 15.2.4Section 15.3.1Section 15.6Section 15.7.2Section 15.13.2Policy Objective RH 9Policy Objective FL1Policy Objective LCM 2Policy Objective LCM 3DM Standard 6DM Standard 7DM Standard 8DM Standard 11DM Standard 28DM Standard 29DM Standard 37DM Standard 38DM Standard 46DM Standard 47DM Standard 50DM Standard 67
Decision Document Summary
Evan O’ Flatharta sought planning permission for a detached single-storey dwelling, garage, and wastewater treatment system at Trá Bháin, Leitir Móir, located within a Class 3 Special Landscape Sensitivity area in the Gaeltacht. Although the applicant successfully demonstrated a longstanding intrinsic link to the area in accordance with rural housing policy, the application was refused due to critical infrastructure deficiencies. The Planning Authority determined that the informal private track ...SOURCE PDFOpen Original