2361143

for 10-years for the development of a solar farm on a site of 125 hectares consisting of the following: 570,952sqm of solar photovoltaic panels on ground mounted steel frames; 18 hardstanding locations, with each containing 3no. electrical skids (each hardstanding location will be surrounded by a palisade fence & gates); underground power & communications cables & ducts, including cabling along the L-8560, L-4506, L-4505 & R347 public roads; 4 joint bays; new internal access tracks; a new access from the R347 public road; upgrade to existing access points along the L-4505 and R347 public roads; access gates; landscaping & biodiversity enhancement measures; security gates; boundary fencing & all associated ancillary development, site works & services. The solar farm will be operational for 40 years. A Natura Impact Statement will be submitted to the planning authority with the application

Refused

Core Refusal Reason

The Inspector recommends granting permission as the proposed development is consistent with national and regional renewable energy policies and the Galway County Development Plan 2022-2028, with further information adequately addressing initial concerns regarding archaeology, traffic safety, and the protection of the Lesser Horseshoe Bat and European sites.

Decision Maker's Conclusion

  • The development is in accordance with the proper planning and sustainable development of the area, aligning with the County Development Plan and the Local Authority Renewable Energy Strategy (LARES).
  • Following the submission of significant further information including geophysical surveys and summertime bat surveys, it is demonstrated that the project will not adversely affect the integrity of nearby European sites or archaeological heritage.
  • The proposed access arrangements and traffic management measures are sufficient to cater for construction and operational traffic without compromising the safety or carrying capacity of the local road network.

Cited Policies (CDP)

Policy Objective RD 2Policy Objective AD 2Policy Objective NR1Policy Objective NNR1Policy Objective NNR2Policy Objective LCM 2Policy Objective NHB 1Policy Objective NHB 2Policy Objective NHB 3Policy Objective NHB 5Policy Objective NHB 9Policy Objective ARC 1Policy Objective ARC 2Policy Objective ARC 4Policy Objective ARC 5Policy Objective ARC 9Policy Objective ARC 10Policy Objective CC 6Policy Objective RE 1Policy Objective RE 4DM Standard 28DM Standard 47DM Standard 50DM Standard 61DM Standard 70

Decision Document Summary

The proposal consists of a solar farm on a 125-hectare site at Cloghboley, Co. Galway, with an operational lifespan of 40 years and an estimated 143MW capacity. The site context is rural and agricultural, characterized by a karst landscape with several turloughs and proximity to multiple Natura 2000 sites, most notably the Lough Fingall Complex SAC. Although Galway County Council originally refused permission based on archaeological concerns, traffic safety, inadequate justification for using ag...
SOURCE PDFOpen Original