2361143
for 10-years for the development of a solar farm on a site of 125 hectares consisting of the following: 570,952sqm of solar photovoltaic panels on ground mounted steel frames; 18 hardstanding locations, with each containing 3no. electrical skids (each hardstanding location will be surrounded by a palisade fence & gates); underground power & communications cables & ducts, including cabling along the L-8560, L-4506, L-4505 & R347 public roads; 4 joint bays; new internal access tracks; a new access from the R347 public road; upgrade to existing access points along the L-4505 and R347 public roads; access gates; landscaping & biodiversity enhancement measures; security gates; boundary fencing & all associated ancillary development, site works & services. The solar farm will be operational for 40 years. A Natura Impact Statement will be submitted to the planning authority with the application
Core Refusal Reason
The Inspector recommends granting permission as the proposed development is consistent with national and regional renewable energy policies and the Galway County Development Plan 2022-2028, with further information adequately addressing initial concerns regarding archaeology, traffic safety, and the protection of the Lesser Horseshoe Bat and European sites.
Decision Maker's Conclusion
- The development is in accordance with the proper planning and sustainable development of the area, aligning with the County Development Plan and the Local Authority Renewable Energy Strategy (LARES).
- Following the submission of significant further information including geophysical surveys and summertime bat surveys, it is demonstrated that the project will not adversely affect the integrity of nearby European sites or archaeological heritage.
- The proposed access arrangements and traffic management measures are sufficient to cater for construction and operational traffic without compromising the safety or carrying capacity of the local road network.