Core Refusal Reason
The Planning Authority is legally precluded from granting a further extension of duration because the development has already benefited from a maximum five-year extension under a previous application (Ref. 18/7027).
Decision Maker's Conclusion
- The subject development has already been granted a previous five-year extension of duration under planning reference 18/7027, which expired on 19th November 2023.
- Section 42(4) of the Planning and Development Act 2000 (as amended) stipulates that a second decision to extend an appropriate period can only be made if the combined duration of the two extensions does not exceed five years.
- As the applicants have already utilized the maximum five-year extension period allowed by legislation, the Planning Authority is prohibited from granting any further extension for the project.
Cited Policies (CDP)
Decision Document Summary
This application sought an extension of duration for a community centre development at Ballyvareen, Kildimo, Co. Limerick, originally permitted under Ref. 12/866. The project included a community centre, car parking, and a new vehicular access to the N69. The Planning Authority refused the application on statutory grounds; the development had already received a five-year extension under Ref. 18/7027, and Section 42(4) of the Planning and Development Act 2000 prevents the granting of further exte...SOURCE PDFOpen Original