the development will consist of a 10-year permission for the construction of a solar PV energy development within a total site area of approximately 131.93ha, to include solar PV panels ground mounted on steel support structures, electrical transformer/inverter station modules, storage containers, CCTV cameras, access tracks, fencing and associated electrical cabling, ducting and ancillary infrastructure. A Natura Impact Statement accompanies this application. Significant further information/revised plans submitted on this application

Granted

Core Planning Reasoning

The Inspector recommends granting permission as the development is consistent with national and regional renewable energy policy objectives, complies with the Meath County Development Plan 2021-2027, and will not seriously injure the visual or residential amenities of the area or adversely affect the integrity of European sites subject to compliance with specific conditions and mitigation measures.

Decision Maker's Conclusion

  • The principle of development is acceptable as it supports national decarbonization goals and aligns with local infrastructure strategies for renewable energy.
  • Potential visual impacts are mitigated by the exclusion of development from the most elevated field (Field 1), which protects regional views and landscape character.
  • Hydrological and ecological risks, particularly regarding the River Dee catchment and Dundalk Bay, can be managed through the enforcement of strict 10m to 30m riparian buffer zones and a comprehensive Construction and Environmental Management Plan.

Cited Policies (CDP)

INF POL 19INF POL 21INF POL 22INF POL 27INF POL 28INF OBJ 23INF OBJ 28INF POL 34INF POL 35INF OBJ 14INF OBJ 38INF OBJ 39INF POL 43HER OBJ 4HER POL 27HER POL 28HER POL 30HER POL 31HER POL 35HER POL 37HER POL 47HER POL 48HER OBJ 48HER POL 52HER OBJ 49HER OBJ 56HER OBJ 60

Decision Document Summary

Highfield Solar Limited proposed a 10-year permission for a solar PV farm and 110kV substation on 130 hectares of agricultural land in North County Meath. The site is characterized by flat grassland with significant drainage networks connected to the Glyde and Dee arterial drainage scheme. Key concerns raised in the appeal included glint and glare, noise, landscape impacts on the Tain Trail, and legal rights of way. The Inspector's assessment focused heavily on environmental protection, recommen...