3274/24
We, NWQ Devco Limited, intend to apply for a 10-year planning permission for development at a site consisting of the CitiGroup Building, 1 North Wall Quay, Dublin 1, DO1 T8Y1. The site is bound by North Wall Quay to the south, Commons Street to the west, Clarion Quay/Alderman Way to the north and an access ramp to the existing basement to the east. The site area is c. 0.88 ha. The proposed development comprises: •Demolition of existing 6 no. storey office building and single-level basement; •Construction of a mixed-use development ranging in height from 9 no. to 17 no. storeys in height (73.4m) over lower ground floor and double basement comprising office accommodation, arts/community/cultural spaces and retail/cafe/restaurant uses; •The development is divided into 4 no. buildings ranging in heights of 12 no. storeys (Block A), 17 no. storeys (Block B), 10 no. storeys (Block C) and 9 no. storeys (Block D); • The overall gross floor area of the development comprises 87,209 sq.m. (excluding double basement of 14,420 sq.m.) including 69,258 sq.m. of office space, 2,371 sq.m. arts/community/cultural uses and 196 sq.m. of retail/café/restaurant space; • Office accommodation is proposed at lower-ground floor to 15th floor with 4 no. double-height office entrance/receptions areas provided at GF level; • 3 no. internal arts/community/cultural spaces are provided in total. 1 no. arts/community/cultural space is provided over lower ground and ground floor level in Block A, 1 no. at 1st floor level with a GF entrance space in Block B and an arts/community/cultural use with viewing deck is provided at 16th floor level in Block B; • External arts/community/cultural space will be provided on the new landscaped park located to the east of the site; •1 no. retail/café/restaurant unit is provided at GF level in Block D; • Outdoor landscaped terraces are provided at 8th, 9th, 10th, 11th, 15th and 16th floor level; • Provision of winter terraces at 4th, 6th and 9th floor level; • Provision of a shared atrium between Block B and Block C; • Green roofs and blue roofs are provided across the scheme; • Provision of a double basement comprising 30 no. car parking spaces, 923 no. bicycle parking spaces, 6 no. motorbike parking spaces and male & female shower and changing facilities at B1 level and plant across B1 & B2 levels; • 2 no. car parking spaces located at street level (32 no. total); •Provision of 2 no. vehicle lifts and 2 no. bike lifts to the basement accessed from Clarion Quay; •The development includes the fill and cover of existing access ramp to existing basement to provide a landscaped park (including external arts/community/cultural space) to the east of the building connecting North Wall Quay with Clarion Quay. The park will include a pedestrian link from North Wall Quay to Clarion Quay •Provision of upgrades to existing public realm within application site including public footpaths along North Wall Quay, Commons Street and Clarion Quay; •All ancillary and associated works to facilitate the development including plant, switch rooms, generators, water tanks, sprinkler plant, ESB substations, landscaping, telecommunications infrastructure, utilities connections and infrastructure. An Environmental Impact Assessment Report and Natura Impact Statement have been prepared in respect of the proposed development and have been submitted with the planning application.
Core Refusal Reason
The proposed 17-storey development is considered excessive in height, bulk, and scale for a site not designated for a landmark building, resulting in serious injury to the visual amenities of the Liffey Quays Conservation Area and unacceptable impacts on the residential amenity of adjacent properties through loss of daylight and sunlight. Furthermore, the wholescale demolition of a functional 25-year-old building is deemed premature and contrary to policies prioritizing the retrofitting and reuse of existing structures.
Decision Maker's Conclusion
- The proposed building's height and massing are at odds with both the immediate and surrounding townscape, presenting an overly dominant and isolated tall building in a sensitive Conservation Area.
- The development would result in significant adverse impacts on neighboring residential amenity, specifically regarding the reduction of daylight and sunlight to the Clarion Quay apartments and the overshadowing of their shared amenity space.
- The Applicant failed to provide an overwhelming justification for the demolition of the existing 25-year-old office building, with sustainability assessments showing that a 'Retain and Extend' option would result in lower whole-life carbon emissions than the proposed new build.
Cited Policies (CDP)
Decision Document Summary
This report concerns an appeal against Dublin City Council's decision to refuse permission for the demolition of the 6-storey Citibank building at 1 North Wall Quay and its replacement with a mixed-use office-led development ranging from 9 to 17 storeys. The site is located within the Dublin Docklands (SDRA 6) and is partially within the Liffey Quays Conservation Area. While the Inspector acknowledged the high architectural quality of the proposal and its potential to improve street-level activi...PDF Document Missing
The original decision document for this case could not be linked. This often happens for older cases or those with restricted documentation.