At existing Schull Pier: Improvements to pier, to include raising existing pier deck and seawall; providing new deck furniture, extension of pier; armourded breakwater; floating pontoon with 24 metres long access gangway from pier. At North Shore of harbour; an access road from R592; reclamation of land from foreshore with associated quay wall; public promenade; walkways; steps to foreshore; lighting and other deck furniture; car park for 130 cars; 10m wide slipway; utility building; recycling area; boat store building; armoured breakwater; pontoon marina with 225 berths and service berth; boat servicing area and associated site works

Refused

Core Refusal Reason

The application for an extension of duration was refused because the development had not commenced, the maximum statutory extension period had already been reached, and a required Appropriate Assessment legally precludes such an extension.

Decision Maker's Conclusion

  • The development permitted under Planning Reference No. 06/1375 had not commenced and no substantial works were carried out prior to the expiration of the appropriate period.
  • The combined duration of the requested extension and the previously granted five-year extension would exceed the maximum limit permitted under Section 42 of the Planning and Development Act 2000.
  • Under Section 42(8) of the Planning and Development Act 2000, an extension of duration cannot be granted where it is determined that an Appropriate Assessment is required.

Cited Policies (CDP)

Decision Document Summary

This application sought an extension of duration for previously permitted improvements to Schull Pier, including the raising of the pier structure at Schull Harbour, Co. Cork. The Planning Authority refused the extension on statutory grounds, noting that the development had not commenced and that the project had already exhausted its allowable extension period under the Planning and Development Act 2000. Furthermore, the determination that an Appropriate Assessment was necessary for the works cr...