23/4245
A 10 year permission for a solar farm consisting of approximately 71,742 photovoltaic panels on ground mounted frames within a site area of 64.55ha, 9 no. single storey inverter/transformer stations, 1 no. single storey spare parts storage container, 1 no. 38kV substation compound with single storey substation building, 1 no. clear span bridge, upgrading of existing agricultural entrances, internal access tracks, security fencing, CCTV, landscaping and all associated development site works
Granted
Analysis not available for this case.
Decision Document Summary
No text availableSOURCE PDFOpen Original