Core Refusal Reason
Failure to meet statutory requirements for an extension of duration under Section 42(1)(a)(ii) of the Planning and Development Act 2000 due to lack of substantial works.
Decision Maker's Conclusion
- Substantial works have not been carried out on the site to date in relation to the original permission.
- The application fails to satisfy the criteria set out in Section 42(1)(a)(ii) of the Planning and Development Act 2000 (as amended).
- The appropriate period for planning reference no. 17/6398 cannot be extended and must be refused.
Cited Policies (CDP)
Decision Document Summary
The applicant sought an extension of duration for the construction of two two-storey dwelling houses and wastewater treatment systems at Collagown, Kilmagner, Fermoy. The local authority refused the application on the grounds that the development had not progressed sufficiently to justify an extension under the Planning and Development Act. Specifically, the lack of substantial works meant the statutory requirements for extending the life of the original permission (Ref: 17/6398) were not met....SOURCE PDFOpen Original