Core Refusal Reason
The application for an extension of duration was refused because substantial works had not been carried out on-site, failing to meet the statutory requirements of the Planning and Development Act.
Decision Maker's Conclusion
- Substantial works have not been carried out to date on the proposed development.
- The application does not satisfy the requirements of Section 42(1)(a)(ii) of the Planning and Development Act 2000 (as amended).
- The appropriate period for the original planning permission (ref. 17/6398) cannot be extended and must be refused.
Cited Policies (CDP)
Decision Document Summary
The applicant sought an extension of duration for planning permission reference 17/6398, which proposed the construction of two two-storey dwelling houses and two wastewater treatment systems at Coolagown, Kilmagner, Fermoy, Co. Cork. The Planning Authority refused the application because the development had not progressed to a stage where substantial works were completed. Under Section 42 of the Planning and Development Act, such an extension is only permissible if significant progress is demon...SOURCE PDFOpen Original