23/5246
10 year permission to develop an Energy Storage System, which will connect to the adjoining ESB Midleton 110kV Electricity Substation. The proposed development will have a projected life span of 30 years. The development will consist of the construction of 1) enclosed battery energy storage system within a site compound on a total of up to c.0.83 hectare site, to include: 1 no. single storey 110kV customer substation, control and switch rooms; up to 13 battery blocks on concrete support structures including heating, ventilation and air conditioning unit (HVAC units); transformer and inverter units; including access tracks and site entrance along existing roadway; associated electrical cabling and ducting; security gates, 2.6m palisade perimeter security fencing; CCTV system; landscaping works and all other associated ancillary infrastructure.