23/6394

Construct 5 no dwellings with associated site works. Extension of Duration to Permission granted under Planning Ref. No. 18/4732

Refused

Core Refusal Reason

Failure to demonstrate that substantial works were carried out during the original permission period to justify an extension of duration under Article 42(a).

Decision Maker's Conclusion

  • The application fails to satisfy the statutory requirements of Article 42(a) of the Planning and Development Act 2000 (as amended).
  • It has not been demonstrated that substantial works were completed in relation to the original permission (18/4732) prior to the extension request.
  • Under Section 45 (3) of the Planning and Development Regulations 2001, the planning authority is unable to extend the appropriate period for the development.

Cited Policies (CDP)

Decision Document Summary

The applicant sought an extension of duration for a previously approved development of five dwellings and associated site works at Lackabane, Donoughmore, Co. Cork. The local authority refused the application on the grounds that the statutory criteria for an extension were not met. Specifically, the developer failed to provide evidence that substantial works had been performed on-site during the initial life of the permission, which is a legal prerequisite for granting an extension under current...