Permission for the construction of the proposed development on agricultural land will comprise of the following; A Battery Energy Storage System with associated infrastructure including a new internal access road approximately 0.8km in length , a 1.6km 33kV double circuit underground cable grid connection to be permitted Ballinrea Solar Farm 110kV substation (Planning ref ABP-317706), to be installed in an excavated trench including underground ducting; modular office and welfare buildings, three steel storage containers and all associated site development and reinstatement works

Granted