25/142

Erection of eight wind turbines with an overall ground to blade tip height of 175m consisting of a rotor diameter of 150m; and a hub height of 100m, Construction of permanent Turbine hardstands and Turbine Foundations, Construction of one temporary Construction Compound with associated temporary site offices parking areas and security fencing, Installation of meteorological mast with a height of 100m, Development of one on-site Borrow pit, Construction of new permanent internal site access roads and upgrade of existing internal site access roads to include passing bays and all associated drainage infrastructure, Development of a permanent internal site drainage network and sediment control systems, All associated underground electrical power and communications cabling connecting the wind turbines to the on-site substation, Biodiversity enhancement measures. Recreational community improvements including the erection of 4 no. permanent information boards relating to cultural heritage and upgrades to amenity tracks across the site, all associated site development works

Refused

Core Refusal Reason

The proposed development would cause significant adverse visual impact on a sensitive upland landscape and scenic routes, while resulting in the unacceptable loss of Annex I peatland habitats.

Decision Maker's Conclusion

  • The height and siting of the turbines would be visually obtrusive and seriously detract from the character of a High Landscape Value area and views from designated scenic routes S28 and S29.
  • The project would necessitate the removal of significant Annex I habitats, including wet heath and blanket bog, leading to a net loss of biodiversity and habitat of special conservation significance.
  • The proposal materially contravenes multiple objectives of the Cork County Development Plan 2022 concerning the protection of visual amenities, scenic prospects, and the county's ecological network.

Cited Policies (CDP)

ET 13-7GI 14-9GI 14-12GI 13-13BE 15-2

Decision Document Summary

The proposal involved the erection of eight wind turbines at Shehy Beg, Co. Cork, within a sensitive 'Ridged and Peaked Upland' landscape. The Planning Authority refused permission because the development would be visually obtrusive from scenic routes and would degrade the character of an area of High Landscape Value. Additionally, the authority determined that the removal of peatland habitats of special conservation significance would result in a permanent negative impact on local biodiversity,...
SOURCE PDFOpen Original